Aurora, CO
|
 |
This
$2.9 million project consists of the complete replacement
of the mechanical systems as well as various
building upgrades and ADA accessibility
issues. All exterior fenestration and roofing
systems are being replaced. The project
design also included a phasing plan that
was coordinated with the Owner's environmental
consultant. This project was completed in
August, 2005. |